|
|
Original
Observation |
Additional
Info |
Recommendation |
|
1. |
Tie-in piece
was not secured by cribbing at both ends causing the pipe to shift while
contractor was grinding the existing pipeline. |
The tie in piece,
which was lying on the ground, was not cribbed because it was not in a final
position. During this time one contractor employee improperly climbed over
the pipe causing it to shift. |
During the
pre-construction safety meeting remind all contractor and company employees
not to climb over any pipe that has not been secured or cribbed in place.
Stress to always think of the consequences to others of your actions during
the job. |
|
2. |
The side-boom
pulled an electrical cord that was running into an excavation while moving
away from the work site. |
A pump was placed
into the trench ahead of the side boom above. The generator powering the pump
was well behind the side boom. When the side boom moved forward a tread
picked up the cord and moved it about 6-8 feet up over the tracks. |
During the
pre-construction safety meeting remind all contractor and company employees
not to move any equipment unless they do a circle of safety check. Where
needed another employee on the ground can assist with the circle of safety. |
|
3. |
Electrical cord in
the excavation was wet causing an electrical shock. |
The employees
described as experiencing the shock were contractor employees. During the tie
in nobody from the contractor crew or company crew said anything about
anybody getting shocked. |
Where and as needed
to avoid any shocks or other electrical issues all extension and welding
cords should be moved and protected to keep them out of the mud and water
during tie in operations. |
|
4. |
Bypass was used to
supply fire control stack at tie-in location #2, which could have
over-pressurized tie-in section. |
At tie in location
#2 the high gas flow caused regs to freeze up. In order to keep the job
progressing the gas was fed through the bypass and controlled at the fire
control stack. |
The existing
regulator panel used by the District will be analyzed by the engineering
staff to determine if the regs need to be upsized or changed out. In the
interim the bypass will not be used to supply gas to the fire control stack. |
|
5. |
Employee slipped on
curb because of mud on his boots. |
Due to the rain
everybody was wet and muddy at both tie in locations. |
Remind employees to
keep their eyes on the path and slow down during operations in wet and
inclement weather. |
|
|
|
|
|
|
|
Original
Observation |
Additional
Info |
Recommendation |
|
6. |
Loss of
communication between tie-in excavations. |
Because it got wet
one cell phone at tie in location #1 stopped working. Another phone was used
to continue to communicate between tie in locations. |
As needed ensure
that spare phones or radios are available to communicate between job locations.
Where possible use all weather radios if available. |
|
7. |
Concern regarding
the fire control stack at location #1 affecting the other stack during the
tie in. |
During the seal
welding the pit boss at location #1 incorrectly removed all the tape off the
band at once when welding started. Initially this resulted in excessive fire
at that location which temporarily affected the other location. The operation
at location #1 was stabilized and both operations continued without affecting
each other. |
Ensure that work
correctly follows the proper steps during hot tie ins. Attending other tie
ins may provide additional field experience needed by some newer employees.
Where needed revise standard 223.0165 to expand welding options and provide
specific procedures to follow. |
|
8. |
Concerns regarding
shoring; (unclear). |
Proper shoring was
installed at both tie in locations. Outside of the work areas there was no
shoring. |
Prior to any work
all shoring should be inspected to ensure that a safe working environment is
established. As needed work with the contractor to correct any problems or
concerns. |
|
9. |
Plastic rain gear
initially worn by some inside the excavation during tie in. |
Once alerted by the
pit boss, the DOM worked with the contractor foreman to have employees remove
any rain gear not suited for use inside the excavation. |
During the
pre-construction safety meeting remind all contractor and company employees
not to wear any plastic or flammable clothing inside the bell holes. |